The temporary Hockey Centre located in the Olympic Park will have two separate pitches, one with spectator seating. The facility will also be used for Paralympic 5-a-side and 7-a-side Football.
Where is it ?
KEY FACTS
Sport: Hockey, Paralympic Five-a-side Football, Paralympic Seven-a side FootballLocation: Within the Olympic Park
New or existing: New
Permanent or temporary: Temporary
Number of events: 4
Find out how to get to the Olympic Park during the London 2012 Games
ABOUT THE HOCKEY CENTRE
The hockey pitches will be installed between July and September 2011, with the surrounding structures set to be built between January and March 2012. The venue will then be ready for the test event in May 2012.
DURING THE GAMES
The Hockey Centre will have two pitches, one with spectator seating and one for use as a warm-up area. As well as the Olympic Hockey competition, the facility will host Paralympic 5-a-side and 7-a-side Football.
AFTER THE GAMES
After the Games the Hockey Centre will move to the north of the Olympic Park, joining a group of facilities in the area known as Eton Manor. It will have 3,000 permanent seats with the ability to increase to up to 15,000 for major events.